Southeastern Wisconsin Poultry Processor
WWTP Upgrade and Phosphorus Removal Study
- type:
- Waste Management
- services:
- Bench-scale testing, Engineering report, Design engineering, Services during construction, Startup and operational assistance
Flow: 75,000 gpd
COD: 12,000 lbs/day
TSS: 7,500 lbs/day
Construction Cost: $1.2 million
Features
Rotary drum screening
Complete mix anaerobic contact process
Activated sludge aerobic process
Land application of waste solids
Effluent discharge to land
ATI designed improvements in a separate project to lower the effluent phosphorus concentrations to <1 mg/L