Massachusetts Dairy Processor



- type:
- Waste Management
- services:
- Waste minimization study, Preliminary engineering report, Design engineering, Services during construction, Startup and operational assistance
Flow: 350,000 gpd
COD: 35,000 lbs/day
FOG: 6,000 lbs/day
TSS: 7,500 lbs/day
Construction Cost: $1.2 million
Features
Separation of wastewater into high-, mid-, and low-strength streams
Mixed high-strength wastewater equalization tank
Complete mix anaerobic contact process
SBR aerobic process for anaerobic effluent and mid-strength wastewater
Effluent discharge to POTW