Minnesota Potato Processor

Wastewater Pretreatment System
 

Industry/Products
  • Potatoes
     
Design Capacity (average)
  • Flow: 1.0 million gpd
  • COD: 160,000 lbs/day
  • TSS: 16,000 lbs/day
     
Construction Cost
  • $3.0 million
Features
  • Primary clarification
  • Centrifuge dewatering of primary solids (animal feed)
  • Fluidized bed anaerobic process
  • Post-anaerobic effluent sulfide removal process
  • Effluent discharge to POTW
Services Provided
  • Preliminary engineering report
  • Design engineering
  • Permitting assistance
  • Services during construction
  • Startup assistance
  • Operations assistance