City of Racine

Bridge Replacement
 

Project Location
  • Racine, Wisconsin
  • Kinzie Avenue over Root River
     
Construction Cost
  • $1.14 million
     
Challenge
  • Historic arch bridge needed replacement due to age, condition and capacity
Features
  • Replaced existing structure in kind with 66" arch
  • Construction of 300 feet of existing approach roadway
  • Riprap used to control erosion
  • Texas rail and aesthetic lighting
  • 200 feet of approach roadway work included in the intersection to the south
  • Bridge design included precast arch plans as well as cast-in-place for contractor's option
  • Fields and wooded park adjacent to bridge
Services Provided
  • Complete design